Textbook Question
Chapter 6, Problem 7E
The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Compute the early and late activity tunes and the slack times. Identify the critical path.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A project consists of the activities in the following list. Times are given in weeks.
Activity
Preceding
Time
A
--
8
B
--
4
C
A, B
7
D
A, B
3
E
C, D
5
F
C, D
6
G
E, F
4
Draw the project network diagram.
Calculate each activity's ES, EF, LS, LF, and Slack using the project activity nodes on the project network diagram.
What is the project completion time?
Identify the critical path
Construct a project network for the following project. The project is completed when
activities F and G are both complete.
Activity
A
B
C
D
E
F
G
Immediate Predecessor
_
_
A
A
C,B
C,B
D,E
A project's activities must be completed in the sequence indicated below.
Activity
Immediately Preceding Activity
Duration in Weeks
A
-
3
B
-
20
C
-
15
D
-
10
E
-
5
F
A
4
G
D
3
H
D, E
10
I
F
3
J
B
10
K
G, H
7
L
B, I
5
The project ends with the intersection of activities: C, J, K and L
1- Use CPM to construct (Draw) the project Network and find the critical path.
2- How long is the project expected to take
Chapter 6 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 6 - How does the WBS differ from the project network?Ch. 6 - How are WBS and project networks linked?Ch. 6 - Why bother creating a WBS? Why not go straight to...Ch. 6 - Why is slack important to the project manager?Ch. 6 - What is the difference between free slack and...Ch. 6 - Why are lags used in developing project networks?Ch. 6 - What is a hammock activity, and when is it used?Ch. 6 - Here is a partial work breakdown structure for a...Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...
Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...Ch. 6 - From the following information, develop an AON...Ch. 6 - The project information for the custom order...Ch. 6 - You have signed a contract to build a garage for...Ch. 6 - You are creating a customer database for the...Ch. 6 - K. Nelson, project manager of Print Software....Ch. 6 - A large Southeast city is requesting federal...Ch. 6 - You are creating a customer database for the...Ch. 6 - You are completing a group term paper. Given the...Ch. 6 - You are managing a product upgrade project for...Ch. 6 - You are creating a database for the Oklahoma City...Ch. 6 - The planning department of an electronics firm has...Ch. 6 - Using Microsoft Project, set up the network and...Ch. 6 - The optical disk project team has started...Ch. 6 - From the following information, compute the early,...Ch. 6 - Given the following information, compute the...Ch. 6 - Given the information in the following lag...Ch. 6 - Given the network below, compute the early, late,...Ch. 6 - The CyClon project team has started gathering...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The G&E Company is preparing a bid to build the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- (PERT-CPM) A small project consisting of eight activities has the following characteristics: -Draw the PERT network for the project. -Prepare the activity schedule for the project showing (Project duration, ES, EF, LS, LF, FLOAT/SLACK). -Determine the critical path.arrow_forwardDraw the network and identify the critical path of following data and total slack time in the network. Also calculate the earliest-latest starting and finishing times for each activity and re-plan the above mentioned network to complete the project in less time.arrow_forwardCalculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify the critical path for the project. Can the project be completed in 30 weeks?arrow_forward
- Based on the given set of activities answer the following: 1. Develop a precedence for each of the activity based on the information provided in the case. 2. Draw a network diagram and also calculate the forward and the backward pass for each of the activities. 3. Identify the paths as well as the critical path for the given project and also determine the slack time for each activity. Note: This question is related to Project Management Course.arrow_forwardFrom the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path.How many days will the project take?arrow_forwardTwo activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.arrow_forward
- In reference to the attached image: Draw the project network, and determine the normal time to complete the project, activity slack times, the critical path(s), and total project costs (i.e., baseline your project), using the Critical Path Method.arrow_forwardConsider the following project activities: Activity Name Immediate Predecessor (list number/ name, separated by ‘,’) Normal Time A - 6 B - 9 C A 12 D A, B 8 E D 9 F C, E 6 G E 5 Fill the given table with the required data and draw the network diagram for the above project activities to find the critical path.arrow_forwardSchedule the following project by using AON network and perform CPM calculations (ES, EF, LS, LF, TF, FF). Also show the critical path.arrow_forward
- Construct this problem. Draw a network diagram, determine the early start, early finish, late start, late finish, and slack times for each activity (table), determine how long the project will take, and which activities are on the critical path.arrow_forwardINSTRUCTIONS: Draw the AON network for Exercise 14 (pg ASSIGNMENT 200 & 201). Complete the forward and backward passes, calculate total slack for each activity, identify the critical path, identify the total project length (or how long it will take to complete the project) based on days, calculate free slack for appropriate activities, and create the Gantt chart. When creating the Gantt chart, you must include slack into the schedule.arrow_forwardThe activities in the following table describe the construction of a new house. Construct the associated project network ACTIVITY PREDECESSORS DURATION (WEEKS) a Create a spreadsheet to calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities. (USING EXCEL ONLY, Vlookup, ISERR etc functions) b. Make a gantt chart.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY