Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9781259666094
Author: Erik W. Larson, Clifford F. Gray
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 6, Problem 8E
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17 working days.
Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Given the following network,
What is the critical path?
How long will it take to complete this project? The duration, in days, follows the letter of each activity.
Can activity B be delayed without delaying the completion of the project? If so, how many days?
You have to manage a project with activities and their respective durations as listed in the table below. Draw a network diagram, Calculate the forward, backward pass, total slack, free slack and identify the critical path.
. Given the following network with activity times in weeks, determine the earliest start and finish times, latest start and finish times, and slack for each activity. Indicate the critical path and the project duration.Â
photo attached-
Calculate and insert ALL missing Earliest Start or Earliest Finish at each Activity.
Calculate and insert ALL missing Latest Start and Latest Finish at each Activity.
Calculate missing Slack at Every Activity on the network Diagram.
List of all possible paths & Total Slacks from Start to finish for each path.
 *Which activities are on the critical path? What is the total slack along the critical path.
Chapter 6 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 6 - How does the WBS differ from the project network?Ch. 6 - How are WBS and project networks linked?Ch. 6 - Why bother creating a WBS? Why not go straight to...Ch. 6 - Why is slack important to the project manager?Ch. 6 - What is the difference between free slack and...Ch. 6 - Why are lags used in developing project networks?Ch. 6 - What is a hammock activity, and when is it used?Ch. 6 - Here is a partial work breakdown structure for a...Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...
Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...Ch. 6 - From the following information, develop an AON...Ch. 6 - The project information for the custom order...Ch. 6 - You have signed a contract to build a garage for...Ch. 6 - You are creating a customer database for the...Ch. 6 - K. Nelson, project manager of Print Software....Ch. 6 - A large Southeast city is requesting federal...Ch. 6 - You are creating a customer database for the...Ch. 6 - You are completing a group term paper. Given the...Ch. 6 - You are managing a product upgrade project for...Ch. 6 - You are creating a database for the Oklahoma City...Ch. 6 - The planning department of an electronics firm has...Ch. 6 - Using Microsoft Project, set up the network and...Ch. 6 - The optical disk project team has started...Ch. 6 - From the following information, compute the early,...Ch. 6 - Given the following information, compute the...Ch. 6 - Given the information in the following lag...Ch. 6 - Given the network below, compute the early, late,...Ch. 6 - The CyClon project team has started gathering...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The G&E Company is preparing a bid to build the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path:arrow_forwardFrom the following information, develop an AON project network. Complete theforward and backward pass, compute activity slack, and identify the critical path.How many days will the project take?arrow_forwardThere are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Each activity in this network can be crashed by 100 hours. The maximum possible reduction in the project duration will be: a. Insufficient information b. 1300 hours c. 500 hours d. 400 hours e. 600 hourarrow_forward
- You are provided with the following information for a project, with activity durations given in weeks:  Activity          Immediate      Optimistic      Most Likely   Pessimistic                                    Predecessor    Time (a)         Time (m)        Time (b)     A                   ____              2                    3                    4     B                   ____              2                    4                    6     C                   A                   1                    2                    3     D                   B                   3                    6                    9     E                   C, D                7                    8                    9     F                    D                   4                    7                    10     G                   E                    3                    4                    5     H                  E, F…arrow_forwardConstruct a Gantt chart for the following set of activities, and indicate the project completion time and slack for each activitarrow_forwardFrom the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path.How many days will the project take?arrow_forward
- Draw the network diagram. Calculate the expected duration and variance of each activity. Calculate the expected duration and variance of the critical path. Calculate the probability that the project will be completed in less than 28 weeks.arrow_forwardConstruct this problem. Draw a network diagram, determine the early start, early finish, late start, late finish, and slack times for each activity (table), determine how long the project will take, and which activities are on the critical path.arrow_forwardDetermine critical path for the project by calculating the slack for each activityarrow_forward
- Suppose you are the project manager for the following project: First, draw a network diagram for the project. Determine the critical path and slack times for all of the tasks. This completes your plan for the project schedule. During project execution, you become aware of the need to change the duration of Task 4 to five days. Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, if any, effects do these changes have on your project? What would have happened if you had not been monitoring the status of the project?arrow_forwardDetermine the amount of slack in each of a project's activities (presented below), and identify those that are on the critical path.arrow_forwardThe project detailed in the table below is contracted for delivery in 11 weeks, with a penalty clause requiring the contractor to pay a penalty of $2000 for each week late. The project must therefore be expedited. The possible reductions and associated costs are shown in the table. Times in the table are given in weeks. Only activity 4 can be expedited two weeks. The other activities can be expedited one week. (a) Determine the critical path(s), the expected duration of the project, and the slack time for each activity (indicate value on network)? What is the total project cost with penalty included? (b) How could the project time be reduced to 11 weeks and what is the total project cost?  Activity Immediate predecessor Normal time Expedited time Normal cost ($) Expedited cost ($)  1 - 4 3 5,000 6,900  2 - 2 2 3,000 3,000  3 1 5 4 7,000 9,200  4 2 6 4 9,000 11,000  5 2 5 4 6,000 7,800…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY