Chapter 10, Problem 4CS
Summary Introduction

Case summary:

Person K is the vice-president of operations at Company J, which received a request for quote of supplying 400 units per week. Employee must be permitted to perform the task for 17 times. The actual times observed were given below:

Number Actual time (minutes)
1 2.05
2 1.92
3 2.01
4 1.89
5 1.77
6 1.8
7 1.86
8 1.83
9 1.93
10 1.96
11 1.95
12 2.05
13 1.79
14 1.82
15 1.85
16 1.85
17 1.99

Performance rating is 115%, fatigue allowance is given as 8%, personal allowance is 6%, and delay allowance is 2%. Workday hour is 7.5 hours and the operators would be paid $12.50 per hour for 8 hours.

To determine: Thecost per unit for the task in direct labor cost.

Blurred answer
Students have asked these similar questions
QUESTION TWO  As an operations management intern at a Limpopo-based company, HGK Holdings, your role is to assist the operationsanalyst with reconfiguring a brownfield project at HGK’s industrial estate in the Limpopo province, code-named LPCHP1. The reconfiguration involves the installation of an advanced biomass unit which generates electrical andthermal energy by burning wood pellets produced as a by-product of the wood processing industry in the province.The process is commonly called cogeneration or CHP (combined heat and power) and it is expected to save cost andincrease operational efficiency at HGK Holdings. The electrical and thermal energy generated is expected to be utilisedin the operations of HGK Holdings. REQUIRED:Answer each of the following questions: 2.1. With the aid of an appropriately labelled Input-Transformation-Output diagram, comprehensively discuss thetransformation process underpinning the operations of LP-CHP1. In your discussion, highlight the transformedand…
how could you break up the task list by each of the five floors
Question 1   Activity   Activity Description Immediate Predecessors Estimated Duration A Excavate — 2 weeks B Lay the foundation A 4 weeks C Put up the rough wall B 10 weeks D Put up the roof C 6 weeks E Install the exterior plumbing C 4 weeks F Install the interior plumbing E 5 weeks G Put up the exterior siding D 7 weeks H Do the exterior painting E, G 9 weeks I Do the electrical work C 7 weeks J Put up the wallboard F, I 8 weeks K Install the flooring J 4 weeks L Do the interior painting J 5 weeks M Install the exterior fixtures H 2 weeks N Install the interior fixtures K, L 6 weeks                           Using the PERT method, draw the network map.  Calculate the earliest start, earliest finish, latest start, latest finish, and slack times for each activity. Display results in a table format.  Calculate the critical path.…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.