Chapter 5, Problem 2PA
a)
Summary Introduction
To determine: The implied utilization of each of the five steps in the process.
b)
Summary Introduction
To determine: The actual and maximum flow rates of the three sandwich types.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Three employees at a fast-food restaurant each perform one of the three activities in serving a customer: take the order, process the order, and deliver the order. The processing time for each activity is given as follows:
Activity
Processing Time
Take the order
30 seconds
Process the order
2 minutes
Deliver the order
1 minute
Assume that the demand is 20 customers/hour. What is the average labor utilization?
a
38.9%
b
85.7%
c
66.7%
d
100%
A local bakery is renowned for its elaborately cecorated sheet cakes. Consider the following process information: One baker is ivailable to prepare the cake batter (measuring and mixing ingredients and then adding it to baking pans). On average, this takes 10 minutes to prepare two cakes, ie. to make enough batter for 2 cakes and to add the batter to 2 cake pans. Move time to add and remove them from the oven is neglig bile, it takes 32 minutes to bake cakes - the bakery has two ovens, each able to hold 2 cakes. The one pastry chef on staff puts on an amazing show that draws a crowd all day-each cake is decorated in 6 minutes. The bakery operates 8 hours per day.
Answer each of the following questions:
a. What is the cycle time (in minutes per cake) of each stage - preparing, baking, and decorating?
b. What is the dally process capacity? Explain.
c. If orders arrive at a rate of 3 cakes every 20 minutes, can the bakery meet the caily demand Explain,
Note: Be clear about how you…
C&A Candy produces two kinds of gumdrops: regular and sugar-free. The data on these gumdrops are given below:
Regular Sugar-Free
30
10
60
30
80
80
Demand (lbs per hour)
Changeover time (min)
Production rate (lbs per hour)
C&A first makes 60 pounds of regular gumdrops, then 20 pounds of sugar-free gumdrops, and then repeats this sequence. What is the utilization of
the production process?
Multiple Choice
O
O
O
25%
20%
50%
40%
Chapter 5 Solutions
OPERATIONS MANAGEMENT LL W/CONNECT CODE
Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQCh. 5 - Prob. 4CQCh. 5 - Prob. 5CQCh. 5 - Prob. 6CQCh. 5 - Prob. 7CQCh. 5 - Prob. 8CQCh. 5 - Prob. 9CQCh. 5 - Prob. 10CQ
Ch. 5 - Prob. 11CQCh. 5 - Prob. 12CQCh. 5 - Prob. 13CQCh. 5 - Prob. 14CQCh. 5 - Prob. 15CQCh. 5 - Prob. 16CQCh. 5 - Prob. 1PACh. 5 - Prob. 2PACh. 5 - Prob. 3PACh. 5 - Prob. 4PACh. 5 - Prob. 5PACh. 5 - Prob. 6PACh. 5 - Prob. 7PACh. 5 - Prob. 8PACh. 5 - Prob. 9PACh. 5 - The help desk at Triple Stacked handles calls from...Ch. 5 - Prob. 11PACh. 5 - A pharmaceutical company creates a compound with a...Ch. 5 - Prob. 13PACh. 5 - Prob. 14PACh. 5 - Prob. 15PACh. 5 - Prob. 16PA
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- XOX Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order Wait time 15. 6 Inspection time 0.8 Process time 1.6 Move time 0.7 Queue time 3. 9 1. Percentage of manufacturing cycle time spent on non-value-added activities 2. Compute the delivery cycle time in daysarrow_forwardXOX Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order Wait time 15.6 Inspection time 0.8 Process time 1.6 Move time 0.7 Queue time 3.9 Compute the delivery cycle time in days. Percentage of manufacturing cycle time spent on non-value-added activities.arrow_forward. Aquatica makes underwater camera housings for divers. The process begins with a solid rectangular block of aluminum that is used to make a single housing. A computer numerically controlled (CNC) machine drills into the block to make the metal “frame” of the housing. Each block requires 15 minutes of drilling. The frame is then chemically treated in a series of baths. There is ample capacity in the treating stage. Finally, a worker must manually attach the various buttons and components to the metal housing. This assembly takes 120 minutes per housing per worker and Aquatica has 6 workers trained to do this task. The CNC machine requires a 30-minute setup time before the production of a batch can begin. a. If the CNC machine produces 14 housings between setups, what would be its capacity (in housings per hour)? b. Assuming the process is supply-constrained, what is the utilization (as a number between 0 and 1) of the CNC machine if it operates in batches of 14 housings? c. Assuming…arrow_forward
- Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. Demand (sandwiches per hour) are Grilled Vegetables = 25, Grilled Chicken = 15, and Pastrami = 10. There are up to five steps in the process of making sandwiches, listed below with processing times. Step Grilled Vegetables Grilled Chicken Pastrami Cut bread 0.75 minutes 0.75 minutes 0.75 minutes Grill 1.4 minutes 1.4 minutes Slice meat 3 minutes Toast 2 minutes 2 minutes 2 minutes Wrap 0.5 minutes 0.5 minutes 0.5 minutes Only 50 percent of customers want their sandwich toasted, no mattor which sandwich is ordered. Suppose Panini employs 1 worker at each step. Instructions: Round all answers to 1 decimal place. (a) What is the implied utilization of each of the five steps in this process? 62.5 % 93.3 % 50.이% 83.3 % 41.7 % Cut Grill Slice Toast Wrap (b) What is the actual and maximum flow rates of the three sandwich types? per hour Veg Chicken per hourarrow_forwardFour employees at a fast-food restaurant each perform one of the four activities in serving a customer: greet customer, take order, process order, and deliver order. The processing time for each activity is given as follows: Greet customer Take order Process order Deliver order A) 50% Assume demand is unlimited. What is the average labor utilization? B) 68% C) 40% Activity D) 162% Processing time per customer 2 seconds 30 seconds 60 seconds 5 secondsarrow_forwardConsider the following batch flow process consisting of three process steps performed by three machines. What is the capacity of the process given the following information? Batch size = 50 parts Step 1 - Processing Time = 1 minute/part; Setup time = 20 minutes Step 2 - Processing Time = 2 minute/part; Setup time = no setup Step 3 - Processing Time = 1.5 minute/part; Setup time = no setup Your answer provided to me was 1.881 parts per minute (which also equals 112.8 parts per hour). I understand how you arrived at such answer. However, per my professor's answer key, states an answer of 30 units per hours (which could be wrong and I want to confirm), but my question is - is there any way the answer could be 30 units per hour? Thank you!arrow_forward
- The magnetic resonance imaging (MRI) unit of St Francis hospital has 2 MRI machines and sees two kinds of patients, “regular” patients and “contrast” patients. The regular patients don’t need any special preparation before imaging but the contrast patients receive an injection of “dye” that enables the physicians to see the images more clearly. Regular patients require 15 minutes in an MRI machine whereas contrast patients take on average 25 minutes in an MRI machine. Over an 8-hour day, the MRI unit receives an average of 25 regular patients and 5 contrast patients. Convert the demand and capacity into "hours of work per day" to answer the following questions: (a) What is the implied utilization (as a %) of the MRI unit? % (Round your answer to whole number) Hint: First calculate the demand in hours of work per day: If there are 5 Contrast patients per day and each Contrast patient takes 25 minutes to 'process', how many 'minutes of work' are demanded every day from…arrow_forwardThe magnetic resonance imaging (MRI) unit of St Francis hospital has 2 MRI machines and sees two kinds of patients, "regular" patients and "contrast" patients. The regular patients don't need any special preparation before imaging but the contrast patients receive an injection of "dye" that enables the physicians to see the images more clearly. Regular patients require 15 minutes in an MRI machine whereas contrast patients take on average 25 minutes in an MRI machine. Over an 8-hour day, the MRI unit receives an average of 25 regular patients and 5 contrast patients. (a) What is the implied utilization (as a %) of the MRI unit? % (b) What are the actual and maximum flow rates through the MRI (patients per day)? regular contrast Actual flow rates Max flow rates.arrow_forwardCubway, the sandwich shop, is run by Jim, Tim and Kim. When a customer arrives, Jim spends 5 minutes taking order from the customer. After this, Tim prepares bread and Kim prepares filling for the order. These activities are performed in parallel, and take 6 and 12 minutes respectively. Jim then assembles the bread and filling, which takes 4 minutes of his time. Finally, Tim spends 1 minutes in delivering the order and taking payment. What is maximum number of sandwiches Cubway can make per hour? (In other words, what is the capacity of the process in sandwiches per hour?)arrow_forward
- Mr. K’s is a very popular hair salon. It offers high-quality hair styling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parenthesis): Activity 1: Welcome a guest and offer homemade herb tea. (10 minutes) Activity 2: Wash and condition hair. (10 minutes) Activity 3: Neck, shoulder, and back stress release massage. (10 minutes) Activity 4: Design the hairstyle and do the hair. (25 minutes) Activity 5: Check out the guest. (5 minutes) Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1. S2 does Activities 2 and Activity 3. S3 does Activities 4 and Activity 5. a) Which server is the bottleneck of the process ? b) What is the utilization of server 2 ? c) What is the…arrow_forwardThe ClickClock corporation produces clocks with six stations. Each station is manned by a human worker, who do the following tasks: These workers get paid $ 10 an hour. Ignore any Station Task Sequence Processing Time (secs) Task Heat-stake lens to bezel Inspect bezel Clean switch holes Install set switch in bezel Total time for A Check switch travel Clean inside bezel Install module in bezel Total time for B Install battery clip in module Heat-stake battery clip in module Install two batteries in module Check switch 14 2 26 A 3 10 Preparation 1 4 18 68 23 B 6 12 Preparation 2 7 25 60 8 20 9 20 Battery 10 22 Installation 11 8. Total time for C 70 Install band Inspect band Total time for D Cosmetic inspection Final test D 12 45 Band 13 13 Installation 58 E 14 4 Packaging 15 71 Preparation Total time for E 75 Place watch and cuff in display box Place cover in display box base 16 20 17 14 Watch 18 Place owner's manual and box into tub 30 packaging Total time for F 64arrow_forwardIn the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 16.65 hours. The time in the welding operation is spent as follows: 3 hours waiting in front of the cutting machine for the batch to start, 3 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 2 hour waiting in front of the welding machine for the batch to start, 2 hour waiting for the setup of the welding machine, 0.65 hour waiting for the other pieces of the batch to go through welding, 0.4 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? percent cetion MacBook Air ww.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,