Concept explainers
(a)
Interpretation: A process flow diagram is to be constructed along withlabeling and the times and percentages.
Concept Introduction:
Any flow unit, when flows through a process, follows L’s Law which states that the Work in Progress and given by,
(a)
Explanation of Solution
Process flow diagram is as follows.
(b)
Interpretation: The throughout in patients is to be determined per hour of each stage in the process.
Concept Introduction:
The throughput of any process is the rate at which outputs are coming out of the process. When the capacity (i.e. the service rate) of a process step is more than or equal to the arrival rate or the demand rate, the throughput will be equal to the demand rate.
On the contrary, if the capacity is less than the demand rate, it means that the process step is a bottleneck and the throughput will be equal to the capacity.
(b)
Explanation of Solution
The throughout in patients per hour of each stage in the process is shown in table below.
Resource | Demand or arrival rate | Capacity or Service rate | Condition | Throughout rate |
RC | 10 per hour | 10 per hour | ||
RRC | 10 per hour | 10 per hour | ||
NP | 10 per hour | 10 per hour | ||
PA | 4 per hour | |||
MD | 4 per hour | |||
BC | 8 per hour | 8 per hour |
(c)
Interpretation: The labor utilization rates are to be calculated and whether these values appropriate. In case they are not appropriate the way the process can be redesigned is to be determined along with then bottlenecks.
Concept Introduction:
The labor utilization is defined as the fraction of time a resource is busy producing output in the long run. It can be calculated by using the following formula.
(c)
Explanation of Solution
However, note that the labor utilization cannot be more than 100% in long run. However, in short run, we can write it as more than 100% using the above formula.
Resource | Demand or arrival rate | Capacity or Service rate | Number of servers (N) | Utilization (U) |
RC | 10 per hour | 1 | 50.00% | |
RRC | 10 per hour | 1 | 100.00% | |
NP | 10 per hour | 1 | 83.33% | |
PA | 1 | 40.00% | ||
MD | 1 | 150.00% | ||
BC | 8 per hour | 1 | 66.67% |
The resource RRC and MD are overloaded as the utilization figures suggest. Similarly, the resource RC and PA are under loaded. Possible improvement strategy is to share the loads of work (as they are similar in nature) between RC and RRC. Also, it should be checked whether the 60/40 ratio of diversion to MD and PA can be modified in order to balance their load
At present, the resource MD, having the capacity less than the arrival rate and thus the flow is constrained at MD. So, it is the bottleneck.
(d)
Interpretation: The way by which the given change affect your answer to the preceding questions.
Concept Introduction:
Any flow unit, when flows through a process, follows L’s Law which states that the Work in Progress and given by,
(d)
Explanation of Solution
Due to the change, the process layout will be as follows.
The throughput rates for each resource will be as follows.
Resource | Demand or arrival rate (D) | Capacity or Service rate | Condition | Throughout rate |
RC | 10 per hour | 10 per hour | ||
RRC | 10 per hour | 10 per hour | ||
NP | 10 per hour | 10 per hour | ||
PA | 4 per hour | |||
MD | 4 per hour | |||
BC | 6 per hour |
The labor utilization of the resources are as follows.
Resource | Demand or arrival rate | Capacity or Service rate | Number of servers (N) | Utilization (U)
|
RC | 10 per hour | 1 | 50.00% | |
RRC | 10 per hour | 1 | 100.00% | |
NP | 10 per hour | 1 | 83.33% | |
PA | 1 | 40.00% | ||
MD | 1 | 200.00% | ||
BC | 1 | 50.00% |
Note that the utilization of MD has just jumped to 200%.
Want to see more full solutions like this?
- Students are going through a three-step process to obtain their ID cards. Each student will first spend 4 minutes at the (only one) registration desk. After that, he/she will visit one of three stations to have his/her picture taken, which takes 10 minutes on average. Finally, there is one machine that prints ID cards, and it takes 2 minutes to print a card. The demand rate is 12 students/hour. The process just completes serving a student. How long does it take to finish serving the following 10 students? Answers: a) 30min b) 40min c) 50min d) 60minarrow_forwardIn the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 11.5 hours. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 1 hour waiting for the setup of the welding machine, 0.5 hour waiting for the other pieces of the batch to go through welding, 0.5 minute at the welding machine, and 1 hour waiting for the transfer to the next department. Determine the exact flow time. What is the value-added percentage of the flow time?(round percentage answer to 4 decimal places.) answer:_______percentarrow_forwardA checkout line at a grocery store takes an average of 3.75 minutes to ring up a customer's order. On average, six customers are in the checkout line. Use the Excel template Little's Law to find the average number of customers per hour that are processed in the checkout line.arrow_forward
- At a cruise ship terminal, each day on average 1000 passengers embark on ships. Onaverage, passengers spend 5 days on their cruise before returning to this terminal. If theflow unit is a passenger, then what are the flow rate and flow time of this process?arrow_forwardHelp ! Choice Bank receives credit card applications that need to be reviewed for a decision. There are two types of applications; preapproved, and non-preapproved. Preapproved applications only need a quick review and therefore take 6 minutes to process. Applications that are not preapproved need a secondary credit check and take 15 minutes to process. The bank receives 10 preapproved applications every hour and 6 applications that are not preapproved every hour. What is the utilization of the process? Group of answer choices 50 % 62.5 % 68.75 % 75 % 100 %arrow_forwardOne of the chair lifts at a ski resort unloads 1800 skiers per hour at the top of the slope.The ride from the bottom to the top takes 12 minutes. How many skiers are riding onthe lift at any given time?arrow_forward
- L. Winston Martin (an allergist) has an excellent system for handling his regular patients who come in just for allergy injections. Patients arrive for injection and fill out a name slip, which is then placed in an open slot that passes into another room staffed by one or two nurses. The specific injections for a patient are prepared, and the patient is called through a speaker system into the room to receive the injection. At certain times during the day, patient load drops and only one nurse is needed to administer the injections. Let’s focus on the simpler case of the two—namely when there is one nurse. Also, assume that patients arrive in a Poisson fashion and the service rate of the nurse is exponentially distributed. During this slower period, patients arrive with an interarrival time of approximately three minutes. It takes the nurse an average of two minutes to prepare the patients’ serum and administer the injection.a. What is the average number you would expect to see in Dr.…arrow_forwardA company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labour content of the jobs needed to produce the shopping carts. Prior to buying the new equipment, the company used five workers, who produced an average of 100 carts per hour. Workers receive $10 per hour, and machine cost was $40 per hour. With the new equipment, it was possible to transfer one of the workers to another department, and equipment cost increased by $10 per hour while output increased by 20 carts per hour. a. The labor productivity under the old system is Blank 1. Fill in the blank, read surrounding text. and the new system is Blank 2. Fill in the blank, read surrounding text. carts per worker per hour. b. Compute the total factor productivity under each of the systems. Old system Blank 3. Fill in the blank, read surrounding text.arrow_forwardBayside General Hospital is trying to streamline its operations. A problem-solving group consisting of a nurse, a technician, a doctor, an administrator, and a patient is examining outpatient procedures in an effort to speed up the process and make it more cost-effective. Listed here are the steps that a typical patient follows for diagnostic imaging: • Patient enters main hospital entrance • Patient takes a number and waits to be called to registration desk • Patient registers • Patient is taken to diagnostic imaging department • Patient registers at diagnostic imaging reception • Patient sits in department waiting area until dressing area clears • Patient changes in dressing area • Patient waits in dressing area • Patient is taken to exam room • Exam is performed • Patient is taken to dressing area • Patient dresses • Patient leaves 1. Create a service blueprint of the procedure and identify opportunities for improvement. 2. Describe what elements of a servicescape would make this…arrow_forward
- Bayside General Hospital is trying to streamline its operations. A problem-solving group consisting of a nurse, a technician, a doctor, an administrator, and a patient is examining outpatient procedures in an effort to speed up the process and make it more cost-effective. Listed here are the steps that a typical patient follows for diagnostic imaging: Patient enters main hospital entrance Patient takes a number and waits to be called to registration desk Patient registers Patient is taken to diagnostic imaging department Patient registers at diagnostic imaging reception Patient sits in department waiting area until dressing area clears Patient changes in dressing area Patient waits in dressing area Patient is taken to exam room Exam is performed Patient is taken to dressing area Patient dresses Patient leaves Create a service blueprint of the procedure and identify opportunities for improvement. Describe what elements of a servicescape would make this…arrow_forwardAn enterprising student has set up an internship clearinghouse for business students. Each student who uses the service fills out a form and lists up to 10 companies that he or she would like to have contacted. The clearinghouse has a choice of two methods to use for processing the forms. The traditional method requires about 20 minutes to reviewthe form and arrange the information in the proper order for processing. Once this setup is done, it takes only two minutes per company requested to complete the processing. The other alternative uses an optical scan/retrieve system, which takes only a minute to prepare but requires five minutes per company for completing the processing. If it costsabout the same amount per minute for processing with either of the two methods, when should each be used? (Answer in Appendix D)arrow_forwardConsider the following two production processes making an electronic component for a navigation system. Both processes consist of 20 stations and operate at a cycletime of 1 minute/unit. Their most error-prone operation is step 9:• Process 1 has a final inspection at the end of the process and has about 300 units of inventory between step 9 and the inspection.• Process 2 has each worker check the work of the previous steps and about 50 units ofinventory between step 9 and the end of the process, roughly equally distributed across theremainder of the process.What would be the information turnaround time for a defect made at station 9?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,