Question
Chapter 3.S, Problem 3P
Summary Introduction
To draw: Determine whether the current sampling plan used by Metro will achieve the levels of α=0.05 and β=0.10.
Introduction: A comparison of the current sampling plan with the binomial distribution table will help to make the decision of whether the levels of α and β can be achieved or not.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
At Webster Chemical, lumps in the caulking compound could cause difficulties in dispensing a smooth bead from the tube. Even when the process is in control, there will still be an average of 4 lumps per tube of caulk. Testing for the presence of lumps destroys the product, so Webster takes random samples. The table below shows the results of the study. Determine the two-sigma upper and lower control limits for this process.
Tube #
Lumps
Tube #
Lumps
Tube #
Lumps
1
6
5
6
9
5
2
5
6
4
10
0
3
0
7
1
11
9
4
4
8
6
12
2
A manufacturer is selling pharmaceuticals that have a weight specification 199.8 to 200.2 mg, with a target value of 200 mg. Before sending its next shipment, the company collects a large sample of product and determines the mean weight of the sample is 199.89 mg, with a standard deviation of 0.035 mg. The process capability index for the current process is ____. Round to three decimal places.
In an acceptance sampling plan developed for lotscontaining 1,000 units, the sample size n is 85. The percentdefective of the incoming lots is 2%, and the probability ofacceptance is 0.64. What is the average outgoing quality
Chapter 3 Solutions
OPERATIONS AND SUPPLY CHAIN MANAGEMENT
Ch. 3.S - Prob. 1QCh. 3.S - Prob. 2QCh. 3.S - Prob. 3QCh. 3.S - Prob. 4QCh. 3.S - Prob. 5QCh. 3.S - Prob. 6QCh. 3.S - Prob. 7QCh. 3.S - The Great Lakes Company, a grocery store chain,...Ch. 3.S - Prob. 2PCh. 3.S - Prob. 3P
Ch. 3.S - The Fast Break Computer Company assembles personal...Ch. 3.S - Prob. 5PCh. 3 - Using Sampling and Statistics to Analyze...Ch. 3 - Prob. 2.1ASCCh. 3 - Prob. 3.1ASCCh. 3 - Prob. 4.1ASCCh. 3 - Prob. 5.1ASCCh. 3 - Prob. 1QCh. 3 - Prob. 2QCh. 3 - Prob. 3QCh. 3 - Prob. 4QCh. 3 - Prob. 5QCh. 3 - Prob. 6QCh. 3 - Prob. 7QCh. 3 - Prob. 8QCh. 3 - Prob. 9QCh. 3 - Prob. 10QCh. 3 - Prob. 11QCh. 3 - Prob. 1PCh. 3 - Prob. 2PCh. 3 - Prob. 3PCh. 3 - Prob. 4PCh. 3 - Prob. 5PCh. 3 - Prob. 6PCh. 3 - Prob. 7PCh. 3 - Prob. 8PCh. 3 - Prob. 9PCh. 3 - Prob. 10PCh. 3 - Prob. 11PCh. 3 - Prob. 12PCh. 3 - Prob. 13PCh. 3 - Prob. 14PCh. 3 - Prob. 15PCh. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - Prob. 18PCh. 3 - Prob. 20PCh. 3 - Prob. 21PCh. 3 - Prob. 22PCh. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 26PCh. 3 - Prob. 27PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 34PCh. 3 - Prob. 36PCh. 3 - Prob. 37PCh. 3 - Prob. 38PCh. 3 - Prob. 39PCh. 3 - Prob. 40PCh. 3 - Elon Corporation manufactures parts for an...Ch. 3 - Prob. 42PCh. 3 - Prob. 44PCh. 3 - Prob. 45PCh. 3 - Prob. 46PCh. 3 - Prob. 47PCh. 3 - Metropolitan General Hospital is a city-owned...Ch. 3 - Prob. 50PCh. 3 - Prob. 51PCh. 3 - The Shuler Motor Mile is a high-volume discount...Ch. 3 - Prob. 1.1CPCh. 3 - Prob. 2.1CPCh. 3 - Improving Service Time at Daves Burgers Daves...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- C-Spec, Incorporated is attempting to determine whether an existing machine is capable of milling an engine part that has a key specification of 4 ± 0.003 inch. After a trial run on this machine, C-Spec has determined that the machine has a sample mean of 4.001 inches with a standard deviation of 0.002 inch. Calculate the capability index ( Cpk��� ) for this machine. Note: Round your answer to 3 decimal places. Should C-Spec use this machine to produce this part? multiple choice Yes Noarrow_forwardC-Spec, Inc., is attempting to determine whether an existing machine is capable of milling an engine part that has a key specification of 5 ± 0.006 inches. After a trial run on this machine, C-Spec has determined that the machine has a sample mean of 5.001 inches with a standard deviation of 0.005 inch. Calculate the Cpk for this machine. (Round your answer to 3 decimal places.)arrow_forward20) Consider a production process that produces tires. A quality engineer has taken 15 samples, each containing 100 tires. The total number of defective tires over the 15 samples is 340. The sample standard deviation is Group of answer choices a) 0.011 b) 0.042 c) 0.005 d) 0.022 e) 0.028arrow_forward
- Using samples of 200 credit card statements, an auditor found the following:Sample 1 2 3 4Number with errors 4 2 5 9a. Determine the fraction defective in each sample.b. If the true fraction defective for this process is unknown, what is your estimate of it?c. What is your estimate of the mean and standard deviation of the sampling distribution of fractions defective for samples of this size?d. What control limits would give an alpha risk of .03 for this process?e. What alpha risk would control limits of .047 and .003 provide?f. Using control limits of .047 and .003, is the process in control?g. Suppose that the long-term fraction defective of the process is known to be 2 percent. What arethe values of the mean and standard deviation of the sampling distribution?h. Construct a control chart for the process, assuming a fraction defective of 2 percent, using twosigma control limits. Is the process in control?arrow_forwardThere are different assumptions when comparing two proportions for small samples than for large samples. True False A confidence interval can be calculated for either the standard deviation or the variance. True False Quality is defined by the extent to which a product satisfies the needs of its users. True Falsearrow_forwardA production manager at a Contour Manufacturing planthas inspected the number of defective plastic molds in 5 randomsamples of 20 observations each. Following are the number ofdefective molds found in each sample:SampleNumber ofDefectsNumber ofObservationsin Sample11202220322041205020Total 6 100Construct a 3-sigma control chart (z 3) with this informationarrow_forward
- Using samples of 200 credit card statements, an auditor found the following: Sample 1 2 3 4 Number with errors 4 2 5 9 a. Determine the fraction defective in each sample. b. If the true fraction defective for this process is unknown, what is your estimate of it? c. What is your estimate of the mean and standard deviation of the sampling distribution of fractions defective for samples of this size? d. What control limits would give an alpha risk of .03 for this process? Page 457 e. What alpha risk would control limits of .047 and .003 provide? f. Using control limits of .047 and .003, is the process in control? g. Suppose that the long-term fraction defective of the process is known to be 2 percent. What are the values of the mean and standard deviation of the sampling distribution? h. Construct a control chart for the process, assuming a fraction defective of 2 percent, using two-sigma control limits. Is the process in control? Can you show me the steps and formulas using excelarrow_forwardThe Big Black Bird Company produces fiberglass camper tops. The process for producing the tops must be controlled so as to keep the number of dimples low. When the process was in control, the defects shown to the right were found in 10 randomly selected camper tops over an extended period of time. Top Dimples 1 7 2 8 3 12 4 9 5 4 6 14 7 7 8 3 9 6 10 8 a. Assuming 10 observations are adequate for this purpose, determine the three-sigma control limits for dimples per camper top. The UCLc equals nothing and theLCLc equals nothing. (Enter your responses rounded to two decimal places. If your answer for LCLc is negative, enter this value as 0.) b. Suppose that the next camper top has 16 dimples. What can you say about the process now? A. The number of defects is greater than the upper control limit, so it is assumed that the process is in…arrow_forwardIf all other factors specified in a sampling plan remain constant, changing the AROfrom 5% to 10% will cause the required sample size to(1) increase.(2) remain the same.(3) decrease.(4) become indeterminate.arrow_forward
- AccuSound Corporation manufactures printed circuits for stereo amplifiers. A common product defect is a “drift” caused by failure to maintain precise heat levels during the production process. Rejects from the 100 percent testing program can be reworked to acceptable levels if the defect is drift. However, in a recent analysis of customer complaints, Marie Allen, the assistant controller, and the quality control engineer determined that normal rework does not bring the circuits up to standard. Sampling showed that about half of the reworked circuits will fail after extended amplifier operation. The incidence of failure in the reworked circuits is projected to be about 10 percent over five years. Unfortunately, there is no way to determine which reworked circuits will fail, because testing will not detect the problem. The rework process could be changed to correct the problem, but the cost-benefit analysis for the suggested change indicates that it is not economically feasible.…arrow_forwardDistinguish between a sampling error and a nonsampling error.How can each be reduced?arrow_forwardAssume the following: A quality manager at a popular restaurant in a New York has accurately measured the Cp & Cpk values associated with the delivery times of the food delivered by her restaurant. He has measured these values over an acceptable time period. The measured values are such that: Cp > 1, and Cpk < 1. Then: a. The process is both cappable and centered between the specification limits. b. The process is neither cappable nor centered between the specification limits. c. The process is cappable but not centered between the specification limits. d. The process is not cappable but centered between the specification limits.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.