Question
Chapter 7, Problem 44P
To determine
The westbound average approach delay and the level of service.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
An approach to a pretimed signal has 30 seconds
of effective red, and D/D/1 queuing holds. The
total delay at the approach is 83.33 veh-s/cycle
and the saturation flow rate is 1000 veh/h. If the
capacity of the approach equals the number of
arrivals per cycle, determine the approach flow
rate and cycle length.
5-10. The following travel times were measured for vehicles
traversing a 1,000-ft segment of an arterial:
Vehicle Travel Time (s)
20.6
2.
21.7
1
3
19.8
4
20.3
5
22.5
6
18.5
7
19.0
8
21.4
Determine the time mean speed (TMS) and space
mean speed (SMS) for these vehicles.
A new freeway ramp meter will be
installed on the Medina onramp to
westbound SR 520. There is 70 ft
from the ramp meter stop line back
to the nearest intersection, and
each stopped vehicle takes up an
average of 20 ft. The desired meter
rate is one vehicle every 10 seconds,
while the arrival rate averages one
vehicle arrival every 11 seconds.
What is the average queue length?
55ft
O 4.5 ft
100ft
90ft
Chapter 7 Solutions
PRIN.OF HIGHWAY ENGINEERING&TRAFFIC ANA.
Ch. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10P
Ch. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Prob. 21PCh. 7 - Prob. 22PCh. 7 - Prob. 23PCh. 7 - Prob. 24PCh. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 33PCh. 7 - Prob. 34PCh. 7 - Prob. 35PCh. 7 - Prob. 36PCh. 7 - Prob. 37PCh. 7 - Prob. 38PCh. 7 - Prob. 39PCh. 7 - Prob. 40PCh. 7 - Prob. 41PCh. 7 - Prob. 42PCh. 7 - Prob. 43PCh. 7 - Prob. 44PCh. 7 - Prob. 45PCh. 7 - Prob. 46PCh. 7 - Prob. 47PCh. 7 - Prob. 48PCh. 7 - Prob. 49PCh. 7 - Prob. 50PCh. 7 - Prob. 51PCh. 7 - Prob. 52PCh. 7 - Prob. 53PCh. 7 - Prob. 54PCh. 7 - Prob. 55PCh. 7 - Prob. 56PCh. 7 - Prob. 57PCh. 7 - Prob. 58PCh. 7 - Prob. 59PCh. 7 - Prob. 60PCh. 7 - Prob. 61PCh. 7 - Prob. 62P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- An observer notes that an approach to a pretimed signal has a maximum of eight vehicles in a queue in a given cycle. If the saturation flow rate is 1440 veh/h and the effective red time is 40 seconds, how much time will it take this queue to clear after the start of the effective green (assuming that approach capacity exceeds arrivals and D/D/1 queuing applies)?arrow_forwardCompute the average approach delay per cycle, given the saturation flow rate of 2400 veh/h and is allocated 24 seconds of effective green in an 80-second signal cycle. Flow at the approach is 500 veh/h. Assume the traffic flow accounts for the peak 15-min period and that there is no initial queue at the start of the analysis period.arrow_forwardQ2: What are the assumptions for using the equations in the queue test? Q3: A signalized intersection, of 105 sec cycle length, the east approach has an effective green time of 20 sec, and the percentage of vehicles arriving during green time is 28%. The west approach has 16 sec green time and 32% of vehicles arriving during the green time. Determine which approach is best coordinated with the upstream signal.arrow_forward
- Traffic demand shown in the figure below uniformly arrives at an intersection. Determine the optimal cycle length and split for the 2- phase signal control. The saturation flow rate of each approach is 2000 [veh/hr of effec-tive green] during the first 40 [sec] after the start of green, but it drops to 1900 [veh/hr of effective green] thereafter. Also, the lost time is assumed to be 5 [sec/phase]. 1000[veh/h] 300[veh/h] 500[veh/h] 1300[veh/h]arrow_forwardPlease calculate the level of service and delay for the westbound left lane group, the westbound approach, and the whole intersection. I provided LOS chart for reference.arrow_forwardThree-phase a pretimed signalized system for T- intersection, the total lost time per phase is 15 sec. Given that PHF for intersection is 0.91. The table below shows information for all movements included in each phase. (Assume the intersection is isolated, and the traffic flow accounts for the peak 15-min period, and there is no initial queue at the start of the analysis period.) 1 Phase Direction Lane group Number of Lanes Volume (veh/h) 2 Northbound Southbound Northbound LT TH & RT ΤΗ I I 250 1800 390 1800 1 270 1600 2- Determine the average vehicle delay for each traffic lane. 3- Evaluate the level of service (LOS) for each traffic lane. 3 Westbound LT 1 250 2500 Saturation flow (veh/lane/hr) 1- Using the Webster method, determine the optimum cycle length and the effective green time for each phase.arrow_forward
- 5. Green terminates at a signalized intersection with 6 vehicles queued for service. The arrival rate for the approach is 1 veh/sec. The departure rate is 2 veh/sec. The cycle length is 100s, 50s of which are effective green. Answer the following: a. What is the total delay (in veh-sec) experienced by all vehicles in this system during the next cycle? (arrow_forwardAn observer notes that an approach to a pretimed signal has a maximum of eight vehicles in a queue in a given cycle. If the saturation flow rate is 1440 veh/h and the effective red time is 40 seconds, how much time will it take this queue to clear after the start of the effective green (assuming that approach capacity exceeds arrivals and D/D/1 queuing applies) (in seconds)? Round off the final answer to whole numberarrow_forwardPlease estimate the minimum cycle length and the green intervals for the following signalized intersection (Figure 7). Please note that the minimum cycle length will be influenced by the design of the phasing diagram. The arrival flow, in pcu/h, for each direction, is illustrated in Figure 7. Please assume any missing values. Lost time following each phase = 2 sec, Amber = 3 sec, Red all = 1 sec, saturation flow 1400 pcu/h. 196, 367, 170 JIL! 400, 140, 215 716 120, 417, 232 400, 433, 184 Figure 7. Intersection Layout and Traffic Flow Dataarrow_forward
- The table shows a 15 minute volume counts during the peak hour on an approach of an intersection. Time 6:00-6:15 pm 6:15-6:30 pm 6:30-6:45 pm 6:45-7:00 pm Volume of traffic 375 380 412 390 a. Determine the peak hour volume b. Determine the peak hour factor c. Determine the design hourly volume (DHV) of the approacharrow_forward(b) An approach to a pretimed signal has 25 seconds of effective green in a 60-second cycle. The approach volume is 500 vph and the saturation flow rate is 1400 vph. Calculate the average vehicle delay assuming D/D/1 queuing.arrow_forwardIn order to determine the DHV from a traffic count worksheet, the first step is to: Group of answer choices Calculate the PHF of each approach Determine which hour has the highest total intersection volume in veh/hr Convert all of the turning counts from veh/15-min to veh/hr Calculate the PHF of the intersectionarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning