Interpretation:To name one potential determinant of the varying capacity

Concept Introduction:

Design Capacity − Design Capacity of a facility is the maximum output of the facility under ideal conditions. There is no delay or stoppages in the process and everything run smoothly.

Effective Capacity − Effective capacity of the facility is actual capacity at which the facility is running or is expected to run. It is always less than the Design Capacity. This is so because of the many factors that delays the process or stops the smooth functioning of the facility

Blurred answer
Students have asked these similar questions
A manufacturer of ballet shoes has determined that its production facility has a design capacity of 300 shoes per week. Theeffective capacity, however, is 230 shoes per week. What is themanufacturer’s capacity utilization relative to both design andeffective capacity if output is 200 shoes per week?
In the bakery, we have established that design capacity is 30 pies per day and effective capacity is 20 pies per day. Currently, the bakery is producing 27 pies per day. What is the bakery’s capacity utilization relative to effective capacity?
Thomas Pang Furniture produced 70,000 Executive chairs per week. The effective capacity is 71,000 chairs. The production line operates 5 days per week with two 6-hour shifts per day. The line was designed to process the Executive chairs at the rate of 1,200 per hour. Determine the design capacity, utilization and efficiency for this plant when producing the Executive chair. Thomas Pang Furniture now needs to increase production of the Executive chairs. A second production line will be added. Effective capacity on this second line is the same as the first line at 71,000 Executive chairs. The first line is operating at a higher efficiency but output on the second line will be no more than 75% because the crew will be primarily new hires. Determine the expected output of this second line.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,