Question
Chapter 7, Problem 15P
Summary Introduction
Interpretation: Late finish time of Task C is to be determined.
Concept Introduction: Late start time: The late start time of a task can be computed by subtracting task time and late finish time of the project.
Late finish time: The rule for late finish time of a task is that it is equal to the smallest late start time of the task’s immediate follower.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
Task C is directly preceded by two tasks–task A and task B. Task A has an expected task completion time of five weeks and an ES time of week 6. Task B has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The ES for activity C is?
You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having 3 backhoes. You receive a call from your partner, Brooker, who desperately needs 1 of your backhoes. You tell Brooker you would be willing to let him have the backhoe if you are still able to complete your project in 11 months. Develop a resource schedule to see if it is possible to complete the project in 11 months with only 2 backhoes. Activities 5 and 6 require 2 backhoes, while activities 1, 2, 3, and 4 require 1 backhoe. No splitting of activities is possible.
Chapter 7 Solutions
Practical Operations Management
Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4P
Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Prob. 21PCh. 7 - Prob. 22PCh. 7 - Prob. 23PCh. 7 - Prob. 24PCh. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 1.1QCh. 7 - Prob. 1.2QCh. 7 - Prob. 1.3QCh. 7 - Prob. 1.4QCh. 7 - Prob. 2.1QCh. 7 - Prob. 2.2QCh. 7 - Prob. 2.3Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- There are six processes in the project time management knowledge area. How do these processes interact in the creation of the project schedule?arrow_forwardThe total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. What are the ES and EF times for Task B now that Task A is complete?arrow_forwardA project has a budget of $300,000 and is expected to last 10 months, with the work results and budget spread evenly across all months. The project just completed its 3rd month, the work is on schedule, and $65,000 has been spent. What is the cost variance? How efficient (in %) must work progress be to complete on time and within budget?arrow_forward
- Please review this Gantt chart it should consist a minimum of 10 tasks Create a partial project schedule using a Gantt Chart (with a minimum of 10 tasks). Can you do it in excel format please Part 1 To prepare a Gantt chart for the FAO-funded Aquaponics Project in Barbados, we need to break down the project into individual tasks and then arrange them in a logical order based on their dependencies. Here is a table format Gantt chart for the project: Task Start Date End Date Duration Dependencies Project planning and initiation 01/01/2021 01/15/2021 15 days - Site selection and preparation 01/16/2021 02/15/2021 30 days Project planning and initiation Design and construction of facility 02/16/2021 04/15/2021 60 days Site selection and preparation Procurement of equipment and tools 04/16/2021 05/15/2021 30 days Design and construction of facility Training program development 05/16/2021 06/15/2021 30 days Procurement of equipment and tools Training program…arrow_forwardAn activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity is on week 10 and $35,000 were spent and is 40% completed. What is the BCWS for this activity?arrow_forwardthe budget of a project is $1 million. The actual cost for work performed is currently $700k. The budgetted cost for work performed is $660k. What is the current progress of the project? The budgeted cost for work scheduled is 700k. Is it on schedule?arrow_forward
- After the first month of a project, the Actual Cost was $400 and the planned cost for the first month was $500. Currently, only 50% of the work have been completed. Based on this information, calculate the following: a.Earned Value b.Cost Variance c.Schedule Variancearrow_forwardThe Cove at UP is looking to open a new location. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. \ tasks predecessors task duration start 0 A start 7 B A 20 C A 34 D B 39 E C,D 6 F D 15 G E,F 33 end G 0 Guillermo has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: \ Metric Description ES Early start time for task EF Early finsh time for task LS Late start time for task LF Late finsh time for task TS Total slack for task FS Free slack for task IS Independent slack for task SS safety slack for task Please provide the CPM result for each of the following metrics: ES_{end} = LS_{D} = TS_{D} = EF_{G} = LF_{G} =arrow_forwardYou will be a Project Manager soon, How can you practice standards for scheduling? Give example or scenario, and apply the key components of proper scheduling.arrow_forward
- You may need to use the appropriate technology to answer this question. Use the following network with activities and times estimated in days to answer the questions. A project network with 13 activities and 17 directed arcs is shown. Activity Start is connected to activity A, to activity B, and to activity C. Activity A is connected to activity D, to activity E, and to activity F. Activity B is connected to activity F. Activity C is connected to activity G and to activity H. Activity D is connected to activity K. Activity E is connected to activity I. Activity F is connected to activity I. Activity G is connected to activity I. Activity H is connected to activity J. Activity I is connected to activity K. Activity J is connected to activity K. Activity K is connected to activity Finish. Activity Finish has no arcs directed to other activities. Activity Optimistic Most Probable Pessimistic A 2 5 6 B 1 3 7 C 5 6 9 D 5 12 14 E 3 4 5 F 9 10 13 G 4 6 8 H 3 6 8 I 5 7 12 J 11 12 13 K 1 3 4…arrow_forwardSelect the process to which this situation can be related to, where The Project manager finds that the Project is behind the planned schedule and brings in more staff to complete the work so that the project can be delivered on time .arrow_forwardConsider the following table of activities A through E in which A is the start node and E is the stop node. Assume all activities require the same resource. On a piece of scratch paper, draw the early-start Gantt Chart associated with this table and determine the following. Assume the project is resource-constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Activities B, C and D all have the same early start date (time). Since there is only one resource, only one of the activities B, C, D can be started on the early start date. Which should be started first?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY