A certain task is expected to take 24 days.The employees in charge worked diligently on the task for 24 days,but he or she accomplished only three-quarters of what is required to be done.The entire project was planned to be completed in 120 days.
1- calculate the task weight for this task.
2-The actual % completion for this task.
3-The actual relative % completion for this task.
Managing a project may be challenging, particularly when many departments must collaborate. When each department works on a project, they'll almost certainly employ a technique that they're most familiar with to get the outcomes they desire. Due to variations in approach and technique, this might make project cooperation across departments challenging.
When working on a bigger project with multiple moving elements that must finally coordinate, project problems might arise. The project will slow down, become less productive, and potentially grind to a standstill if these pieces are not properly aligned. Project integration management is used to bring together the many departments and aspects of a project.
Project integration management is a technique for coordinating many activities. It takes the many processes utilised in a project and ensures that they are coordinated.
Making trade-offs is how project integration management does this. That implies you won't be able to have it all if…
In the portion of the management plan devoted to the project titled "work that needs to be done," what are three components that need to be included?
Chapter 7 Solutions
Practical Operations Management
Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4P
Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Prob. 21PCh. 7 - Prob. 22PCh. 7 - Prob. 23PCh. 7 - Prob. 24PCh. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 1.1QCh. 7 - Prob. 1.2QCh. 7 - Prob. 1.3QCh. 7 - Prob. 1.4QCh. 7 - Prob. 2.1QCh. 7 - Prob. 2.2QCh. 7 - Prob. 2.3Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The information below shows the order in which the activities of a project occur alongwith the time taken for each activity:Q must follow PR must follow PS must follow PT must follow SU must follow S and TV must follow S and TW must follow P, Q, R, S, T , U, VP takes 8 minutesQ takes 6 minutesR takes 6 minutesS takes 3 minutesT takes 3 minutesU takes 7 minutesV takes 7 minutesW takes 18 minutesConstruct an activity network to represent the project information given. Include the earlystart, early finish, late start and late finish times for EACH activity. Hence, determine thecritical path for the project.arrow_forwardA project has a budget of $300,000 and is expected to last 10 months, with the work results and budget spread evenly across all months. The project just completed its 3rd month, the work is on schedule, and $65,000 has been spent. What is the cost variance? How efficient (in %) must work progress be to complete on time and within budget?arrow_forwardWhich activities or tasks are crucial to the project-that is, which activities will cause the entire project to be delayed if they are delayed?arrow_forward
- the budget of a project is $1 million. The actual cost for work performed is currently $700k. The budgetted cost for work performed is $660k. What is the current progress of the project? The budgeted cost for work scheduled is 700k. Is it on schedule?arrow_forwardPrimavera/Oraclewww.oracle.comGather information about Primavera project planning and scheduling software. Come toclass prepared to discuss the features of this software.arrow_forwardTypically, a project is a one-time action that must be finished within a specified time frame? why?arrow_forward
- Briefly describe 'Parkinson's Law' and 'Murphy's Law'. One sentence each. Then briefly in 3-6 sentences, please explain why these 'Laws' are relevant in project planning in regard to schedule, risk, cost, and resources (especially the 'people resource')..arrow_forwardPresent five (5) main tasks that you could divide the entire project into to get the results you want. For each parent task, determine a related child task. Present a schedule of the estimated duration of each of the main tasks broken down in the previous instruction. Determine the total time of the project. Mention the aspects that you must consider during the project control stage. Establish the most important elements to consider for closing the project.arrow_forwardCase Project 3 Case Project: Think of all the tasks that you perform when you purchase a car. Include any research, decisions, or financial issues that relate to the purchase. Create a WBS that shows all the tasks, their estimated duration, and any predecessor tasks.arrow_forward
- A project consists of three tasks: A, B, and C. Task A is known to take five days forsure. Tasks B and C are each dependent on A. B takes five days. C takes seven dayswith a probability of 0.5 and three days with a probability of 0.5. What is the expectedcompletion time of the project?a. 8 daysb. 10 daysc. 11 daysd. 12 daysarrow_forwardMohammed is planning to renovate his house garden; he is wondering how long it may take him to achieve this project so he asked his friends who went through the same project. Ahmed told him it will take 7 days, Faisal told him it will take 10 days and Salem told him it will take 15 days. How long it will take Mohammed to renovate his garden following the Beta distribution?arrow_forwardyour supervisor has just informed you that the deadline for completing your team’s goal has been moved up by two weeks. How many people are on your team? What are their roles? What are their skill sets? How can these be rearranged to meet the new requirements? Are there enough human resources to complete the project two weeks earlier? If not, how can you increase the team’s capacity? Are there aspects of the project that can be condensed or skipped? What are the implications of skipping or condensing tasks? Are there costs to be considered with these changes? How can you leverage what you’ve learned about solving problems in teams to meet the new project requirements? How do you intend to communicate the new requirements to the team in order to gain their buy-in?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY