Concept explainers
a
Interpretation:
Critical path of this network.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
a
Explanation of Solution
Project network diagram for given information:
The below image shows the project network with the early start, early finish, late start and late finish:
The critical path in the project network:
The paths in the given project network are as follows:
A-E-J
A-C-F
B-D-G-I-J
B-D-H-I-J
There are four paths in the project network.
Out of the above mentioned path, the path that has the equal early start and late start at the same time early finish and late finish are the critical path.
Here two paths are satisfying the above condition, which are as follows:
A-C-F
B-D-H-I-J
When the network has more than one critical path, the path, which has the maximum project completion time, should be selected.
Hence, the critical path is B-D-H-I-J.
b
Interpretation:
Completion time of the project.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
b
Explanation of Solution
When the network has more than one critical path, the path, which has the maximum project completion time, should be selected.
A-C-F
B-D-H-I-J
Hence, the critical path is B-D-H-I-J.
As the critical path is determined as B-D-H-I-J, the project completion time is 11 days.
c
Interpretation:
The slack of activity A.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
c
Explanation of Solution
The slack of the activity is calculated by subtracting the early start from the late finish.
Hence, the slack of activity A is 0.
d
Interpretation:
Task to be crashed and its cost.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
d
Explanation of Solution
The cost of crashing.
It is given that the paths should be crashed and the total time of the path should not exceed 8 days. The cost to crash Activity B is $500 per crash, Activity H is $200 per crash, and all eligible activities are $100 per crash.
Use the following steps to crash the activities:
The paths and the total task time to complete the path within 8 days is shown below:
Path A-E-J:
Total task time is calculated by adding the duration of all the activities in the path.
Hence, the total task time is 9 days. It exceeds 8 days. Thus, the path should be crashed. Activity A and Activity J cannot be crashed as the duration is 1. Activity E should be crashed from 7 days to 6 days.
Hence, the total task time is 4 days. It does not exceed 8 days. Thus, the path cannot be crashed.
Path B-D-G-I-J:
Total task time is calculated by adding the duration of all activities in the path.
Hence, the total task time is 10 days. It exceeds 8 days. Thus, the path should be crashed. However, it costs $500 to crash one day of Activity B. Thus, Activity D and Activity G can be crashed from 2 days to 1 day.
The cost for crashing is $200 as the crashing was done for two days in Activity D and Activity G. It is given that the activities except for Activity B and H cost $100 per day.
Path B-D-H-I-J
Total task time is calculated by adding the duration of all the activities in the path.
Hence, the total task time is 10 days. It exceeds 8 days. Thus, the path should be crashed. Activity I, Activity D (crashed in the previous step), Activity J cannot be crashed as the duration is 1 day. Activity B can be crashed. However, it costs $500 to crash one day of Activity B. Thus, Activity H can be crashed from 3 days to 2 days.
The cost for crashing is $400 as the crashing was done for two days in Activity H. It is given Activity H costs $100 per day.
Total crashing cost:
Total crashing cost is calculated by adding all the crashing cost done in the previous steps.
Want to see more full solutions like this?
Chapter 7 Solutions
Practical Operations Management
- You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…arrow_forwardYou may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…arrow_forwardTwo international banks are integrating two financial processing software systems as a result of their merger. Preliminary analysis and interviews with all parties involved resulted in the following project information. The “systems integration team” for this project plans to define and manage the project on two levels. The following activities represent an aggregate view, and within each activity is a more detailed view with subtasks and project networks defined. All times are in weeks. A: Draw the project network. B: Identify the critical path. C: What is the total project completion time?arrow_forward
- The required data for a small project consisting of different activities are given below: a) Draw the network diagram for the project and find the normal and minimum project lengthb) If the project is to be completed in 21 days with minimum crash cost which activities should be crashed to how many days?arrow_forwardThe managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. Draw the project network, and compute the expected time and variance for each activity. Develop an activity schedule for this project, compute activity slack time and identify critical path.arrow_forwardYou are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calcu-late the free slack and total slack for all noncritical activities.ID Description Predecessor Time (days)A Systems design None 2 B Subsystem A design A 1C Subsystem B design A 1D Subsystem C design A 1E Program A B 2F Program B C 2G Program C D 2H Subsystem A test E 1I Subsystem B test F 1J Subsystem C test G 1K Integration H, I, J 3L Integration test K 1arrow_forward
- Suppose you are the project manager for the following project: First, draw a network diagram for the project. Determine the critical path and slack times for all of the tasks. This completes your plan for the project schedule. During project execution, you become aware of the need to change the duration of Task 4 to five days. Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, if any, effects do these changes have on your project? What would have happened if you had not been monitoring the status of the project?arrow_forwardIn reference to the attached image and data below: What are the final recommendations? Step A we know: Critical Path = A, B, H, I, J; Project Time = 40 Weeks; Total Cost = 364,000 Step B we know: To crash the critical path I would crash A by 1 week, B by 2 week, H by 2 week and C by 3 week. This would not alter the critical path, only the time line. Steps C we know: Modeling uncertainty in activity times. In this case I would use the activity times and determine the Variances and the Standard Deviation. Using “best case” (x) and “worst case” (y) scenarios for activity times the formula’s would be (x-y)/6 and (x-y)^2/36.arrow_forwardThe managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. What is the probability that project can be completed two months early?arrow_forward
- Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table. Electric Motor Project Data Activity Normal Time(days) Normal Cost ($) Crash Time (days) Crash Cost ($) ImmediatePredecessor(s) A B C D E F G H 4 7 5 6 3 11 4 3 1000 1400 2000 1200 900 2500 800 300 3 4 4 5 2 6 3 1 1300 1200 2700 1400 1100 3750 1450 500 None None None A B C D,E F,G a. Draw the project network diagram.b. What completion date would you recommend?arrow_forwardWhen designing and assessing a project network: On a Forward Pass -- why do we use the higher early-finish time value of two or more merging activities? And on a Backward Pass -- why do we use the lower latest-start value of two or more activities following a Burst activity?arrow_forwardUse the Program Evaluation and Review Technique to represent the project in an activity network. In conjunction with the Critical Path Method, use the activity network to find the shortest time possible to complete the project, to identify the critical jobs in the project, and to determine the earliest and latest that each activity can start and finish without making the project completion longer.a=1, b=1, c=6, d=5, e=2, f=5; andab=1x1=1, bc=1x6=6, cd=6x5=30, de=5x2=10, ef=2x5=10, af=1x5=5.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.