Concept explainers
Case Summary:
A business school plans to organize the graduation ceremony in the University’s indoor space facility. The university granted permission to the institute to use the indoor space only for six hours from 11 AM to 5 PM just after the completion of another graduation ceremony being hold by the institute of engineering. Just after finishing the graduation ceremony of the business institute, the institute of arts will take the charge of the indoor space for their function.
Interpretation:
The director of the events is little worried that the engineering institute will not start their program at the given time to finish the program by 5 PM, considering that everything will go as planned than the delay caused by the Engineering institute to start the business school’s work without causing the business school program to run past 5 PM and cause delay for the institute of Arts and sciences.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Practical Operations Management
- In a company a production activity has been setup, and the management want to know the expected activity time of it where a , b and m are 2 , 7 and 3 month's respectively. Calculate the variance of the activity with expected activity time.arrow_forwardThe Peabody Coal Corporation recently completed the final feasibility report for a new general ledger accounting system. It has hired a consulting firm to program and install the new system. The consulting firm is charging $350,000 for the remaining tasks to be performed. These tasks are to be performed over the next 10 months as detailed in the Gantt chart in the diagram. The consulting firm is extremely concerned with the project staying on schedule because it is receiving a flat fee. The release of the final payment is contingent upon the system performing as stated in the contract and upon Peabody receiving appropriate documentation of the system.Requireda. Prepare a PERT diagram and indicate the critical path.b. What happens to the time frame of the implementation of the project if the manufacturer is 4 weeks late shipping the hardware?c. What happens if the data conversion does not go smoothly and takes an additional 3 weeks? d. Who should conduct the postimplementation review?…arrow_forwardTask C is directly preceded by two tasks–task A and task B. Task A has an expected task completion time of five weeks and an ES time of week 6. Task B has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The ES for activity C is?arrow_forward
- Consider a construction project with the following data on precedence relationships, durations, and costs: Activity Immediate predeccessor (s) Normal Time (days) Normal Cost ($) Crash Time (Days) Crash Cost ($) A - 6 120 4 170 B - 4 120 2 220 C A 3 195 2 270 D A 4 320 2 520 E B, C 7 700 4 1075 F D, E 5 650 2 1100 G E 10 1600 6 2300 F and G are the terminal activities of the project. (a) Find the critical path. (b) Find the project completion time and the corresponding cost. (c) Suppose it is required to complete the project in 22 days. Find which activities to crash and by how much, to yield the minimum project cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardEnvironment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. Suppose that some of the activities in the Environment Recycling, Inc. project can be crashed.The table below shows the crash times and costs associated with performing the activities at their original (normal) times and also for the crash times (all times are in weeks). Normal Crash Normal Crash Activity Predecessor(s) Time Time Cost Cost A — 6 5 $490 $640 B A 9 7 1,800 2,400 C A 8 7 860 1,060 D — 7 6 620 920 E B, C, D 9 7 1,900 2,300 F D 4 2 820 1,320 G D 4 3 620 870 H E 5 4 500 710 I F, G, H 7 5 950 1,550 Choose the correct network for the project. The correct network is C . Identify the critical path. The critical path is A-B-E-H-I. What is the total project completion time? Round your answer to the nearest whole number. ___ weeks What is the lowest cost solution if…arrow_forwardWilliam, a project manager, has a workload of 25,000 hours that needs to be completed in 30 weeks. He has a team of 20 people who work five 8-hour days per week. He notices that in the 30-week period, there are three holidays and 6 members have each requested 8 days off. Given this information, William is _____ short of completing his workload. Question options: 23,136 hours 1,864 hours 480 hours 1,480 hours 384 hoursarrow_forward
- The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 11 10 22 B 10 8 13 C 8 4 19 D 6 4 16 E 1 3 30 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job A B C D E Using the EDD (earliest due date) decision rule for sequencing the jobs,…arrow_forwardThe Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 11 10 22 B 10 8 13 C 8 4 19 D 6 4 16 E 1 3 30 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job ▼ A E B C D ▼ E C B D A ▼ A B C E D ▼ A B D C E ▼ C B D E Aarrow_forwardThe mowry machine shop still has five jobs to be processed as of 8A.M today (day 29) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in order of arrival: Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 12 4 10 B 7 3 24 C 5 10 16 D 3 8 7 E 1 4 13 Develope serpate schedules by using the FCF and EDS rules. Using FCF, the order is Using EDS, the order is The average flow time and average days past due are. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward
- The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 8 3 23 B 6 10 15 C 4 8 6 D 2 4 12 E 1 6 9 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job A B C D E Using the EDD (earliest due date) decision rule for sequencing the jobs, the…arrow_forwardThe Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 8 3 23 B 6 10 15 C 4 8 6 D 2 4 12 E 1 6 9 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job A B C D E Using the EDD (earliest due date) decision rule for sequencing the jobs, the…arrow_forwardthe Problem attached as there is some drawing I can not add it herearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.