Question
Book Icon
Chapter 7, Problem 14P
Summary Introduction

Interpretation: Early finish time of Task C is to be determined.

Concept Introduction: Critical path is the arrangement of project activities which gives an estimate time duration under which project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.

PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.

Early start time: The rule for early start time of a task is that it is equal to largest early finish time of the task’s immediate predecessors.

Early finish time: The early finish time of a task is addition of both task time and early start time of the task.

Late start time: The late start time of a task can be computed by subtracting task time and late finish time of the project.

Late finish time: The rule for late finish time of a task is that it is equal to the smallest late start time of the task’s immediate follower.

It is given that there are two immediate predecessors for Task C,that is, Task A and Task B. It is given that early finish time of task A is 3 days and task B is 5 days.

Blurred answer
Students have asked these similar questions
Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. What are the ES and EF times for Task B now that Task A is complete?
An activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity is on week 10 and $35,000 were spent and is 40% completed. What is the Earned Value for this activity?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY