Interpretation: Early finish time of Task C is to be determined.
Concept Introduction: Critical path is the arrangement of project activities which gives an estimate time duration under which project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.
Early start time: The rule for early start time of a task is that it is equal to largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is addition of both task time and early start time of the task.
Late start time: The late start time of a task can be computed by subtracting task time and late finish time of the project.
Late finish time: The rule for late finish time of a task is that it is equal to the smallest late start time of the task’s immediate follower.
It is given that there are two immediate predecessors for Task C,that is, Task A and Task B. It is given that early finish time of task A is 3 days and task B is 5 days.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Practical Operations Management
- A project has a budget of $300,000 and is expected to last 10 months, with the work results and budget spread evenly across all months. The project just completed its 3rd month, the work is on schedule, and $65,000 has been spent. What is the cost variance? How efficient (in %) must work progress be to complete on time and within budget?arrow_forwardThere are six processes in the project time management knowledge area. How do these processes interact in the creation of the project schedule?arrow_forwardYou have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having 3 backhoes. You receive a call from your partner, Brooker, who desperately needs 1 of your backhoes. You tell Brooker you would be willing to let him have the backhoe if you are still able to complete your project in 11 months. Develop a resource schedule to see if it is possible to complete the project in 11 months with only 2 backhoes. Activities 5 and 6 require 2 backhoes, while activities 1, 2, 3, and 4 require 1 backhoe. No splitting of activities is possible.arrow_forward
- Task C is directly preceded by two tasks–task A and task B. Task A has an expected task completion time of five weeks and an ES time of week 6. Task B has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The ES for activity C is?arrow_forwardPlease review this Gantt chart it should consist a minimum of 10 tasks Create a partial project schedule using a Gantt Chart (with a minimum of 10 tasks). Can you do it in excel format please Part 1 To prepare a Gantt chart for the FAO-funded Aquaponics Project in Barbados, we need to break down the project into individual tasks and then arrange them in a logical order based on their dependencies. Here is a table format Gantt chart for the project: Task Start Date End Date Duration Dependencies Project planning and initiation 01/01/2021 01/15/2021 15 days - Site selection and preparation 01/16/2021 02/15/2021 30 days Project planning and initiation Design and construction of facility 02/16/2021 04/15/2021 60 days Site selection and preparation Procurement of equipment and tools 04/16/2021 05/15/2021 30 days Design and construction of facility Training program development 05/16/2021 06/15/2021 30 days Procurement of equipment and tools Training program…arrow_forwardAn activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity is on week 10 and $35,000 were spent and is 40% completed. What is the BCWS for this activity?arrow_forward
- If Task B is delayed by 2 days, which of the following task will be directly impacted? Task Duration Predecessor A 3 days - B 5 days A C 4 days B D 2 days B E 1 day C, D F 1 day E a. Task F b. Task C c. None of the above. d. Task E e. Task Darrow_forwardA certain task is expected to take 24 days.The employees in charge worked diligently on the task for 24 days,but he or she accomplished only three-quarters of what is required to be done.The entire project was planned to be completed in 120 days. 1- calculate the task weight for this task. 2-The actual % completion for this task. 3-The actual relative % completion for this task.arrow_forwardThe Cove at UP is looking to open a new location. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. \ tasks predecessors task duration start 0 A start 7 B A 20 C A 34 D B 39 E C,D 6 F D 15 G E,F 33 end G 0 Guillermo has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: \ Metric Description ES Early start time for task EF Early finsh time for task LS Late start time for task LF Late finsh time for task TS Total slack for task FS Free slack for task IS Independent slack for task SS safety slack for task Please provide the CPM result for each of the following metrics: ES_{end} = LS_{D} = TS_{D} = EF_{G} = LF_{G} =arrow_forward
- Mohammed is planning to renovate his house garden; he is wondering how long it may take him to achieve this project so he asked his friends who went through the same project. Ahmed told him it will take 7 days, Faisal told him it will take 10 days and Salem told him it will take 15 days. How long it will take Mohammed to renovate his garden following the Beta distribution?arrow_forwardthe budget of a project is $1 million. The actual cost for work performed is currently $700k. The budgetted cost for work performed is $660k. What is the current progress of the project? The budgeted cost for work scheduled is 700k. Is it on schedule?arrow_forwardAfter the first month of a project, the Actual Cost was $400 and the planned cost for the first month was $500. Currently, only 50% of the work have been completed. Based on this information, calculate the following: a.Earned Value b.Cost Variance c.Schedule Variancearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.