Interpretation: Duration of the project is to be calculated.
Concept Introduction: Critical path is the arrangement of project activities which gives an estimate time duration under which project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.
Early start time: The rule for early start time of a task is that it is equal to largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is addition of both task time and early start time of the task.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Practical Operations Management
- Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.arrow_forwardThe information below shows the order in which the activities of a project occur alongwith the time taken for each activity:Q must follow PR must follow PS must follow PT must follow SU must follow S and TV must follow S and TW must follow P, Q, R, S, T , U, VP takes 8 minutesQ takes 6 minutesR takes 6 minutesS takes 3 minutesT takes 3 minutesU takes 7 minutesV takes 7 minutesW takes 18 minutesConstruct an activity network to represent the project information given. Include the earlystart, early finish, late start and late finish times for EACH activity. Hence, determine thecritical path for the project.arrow_forwardMohammed is planning to renovate his house garden; he is wondering how long it may take him to achieve this project so he asked his friends who went through the same project. Ahmed told him it will take 7 days, Faisal told him it will take 10 days and Salem told him it will take 15 days. How long it will take Mohammed to renovate his garden following the Beta distribution?arrow_forward
- You may need to use the appropriate technology to answer this question. Use the following network with activities and times estimated in days to answer the questions. A project network with 13 activities and 17 directed arcs is shown. Activity Start is connected to activity A, to activity B, and to activity C. Activity A is connected to activity D, to activity E, and to activity F. Activity B is connected to activity F. Activity C is connected to activity G and to activity H. Activity D is connected to activity K. Activity E is connected to activity I. Activity F is connected to activity I. Activity G is connected to activity I. Activity H is connected to activity J. Activity I is connected to activity K. Activity J is connected to activity K. Activity K is connected to activity Finish. Activity Finish has no arcs directed to other activities. Activity Optimistic Most Probable Pessimistic A 2 5 6 B 1 3 7 C 5 6 9 D 5 12 14 E 3 4 5 F 9 10 13 G 4 6 8 H 3 6 8 I 5 7 12 J 11 12 13 K 1 3 4…arrow_forwardA certain task is expected to take 24 days.The employees in charge worked diligently on the task for 24 days,but he or she accomplished only three-quarters of what is required to be done.The entire project was planned to be completed in 120 days. 1- calculate the task weight for this task. 2-The actual % completion for this task. 3-The actual relative % completion for this task.arrow_forwardTrue or False? Project scheduling is a determination of the order and duration of activities required to complete a projectarrow_forward
- the budget of a project is $1 million. The actual cost for work performed is currently $700k. The budgetted cost for work performed is $660k. What is the current progress of the project? The budgeted cost for work scheduled is 700k. Is it on schedule?arrow_forwardBriefly describe 'Parkinson's Law' and 'Murphy's Law'. One sentence each. Then briefly in 3-6 sentences, please explain why these 'Laws' are relevant in project planning in regard to schedule, risk, cost, and resources (especially the 'people resource')..arrow_forwardWhat is the optimal plan for expediting some activities so as to minimize the total cost of performing the project within the deadline?arrow_forward
- A Gantt chart is a project schedule that superimposes project activities on a time line. Part 2 True Falsearrow_forwardGiven a project with three paths and their corresponding path lengths: A-B-C: 25 days, A-D-F: 15 days, and B-C-D-E: 20 days; which of the following statements is TRUE? * Activity B has the most slack The expected duration of the project is 60 days The earliest project completion time is 15 days The critical activities are A, B and Carrow_forwardPlease review this Gantt chart it should consist a minimum of 10 tasks Create a partial project schedule using a Gantt Chart (with a minimum of 10 tasks). Can you do it in excel format please Part 1 To prepare a Gantt chart for the FAO-funded Aquaponics Project in Barbados, we need to break down the project into individual tasks and then arrange them in a logical order based on their dependencies. Here is a table format Gantt chart for the project: Task Start Date End Date Duration Dependencies Project planning and initiation 01/01/2021 01/15/2021 15 days - Site selection and preparation 01/16/2021 02/15/2021 30 days Project planning and initiation Design and construction of facility 02/16/2021 04/15/2021 60 days Site selection and preparation Procurement of equipment and tools 04/16/2021 05/15/2021 30 days Design and construction of facility Training program development 05/16/2021 06/15/2021 30 days Procurement of equipment and tools Training program…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.