Chapter 7, Problem 20P
Summary Introduction

Interpretation: Duration of the project is to be calculated.

Concept Introduction: Critical path is the arrangement of project activities which gives an estimate time duration under which project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.

PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.

Early start time: The rule for early start time of a task is that it is equal to largest early finish time of the task’s immediate predecessors.

Early finish time: The early finish time of a task is addition of both task time and early start time of the task.

Blurred answer
Students have asked these similar questions
A project consists of Six activities: A,B,C,D, E, F. A and B have no preceding activities, but activity C requires that activity B must be completed before C can begin. Activity D cannot start until both activities A and B are complete. Activity F can start any time. Activity E requires activities A and C to be completed before it can start. If the activity times are A: 10 days; B: 4 days; C: 8 days; D: 3 days, E = 2 days, and F: 1 day, * Find out the minimum time possible to complete this project. * Are there any critical path activities? Which one are those?
There are six processes in the project time management knowledge area. How do these processes interact in the creation of the project schedule?
A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the totalcompletion time for the project?a. 3 days, because this is the minimum timeb. 7 days, because this is the maximum timec. 20 days, because this is the sum of the timesd. It is not possible to determine the total completion time from the given information
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY