Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 12, Problem 51AP
Summary Introduction
Interpretation:
Proportion of points on chart would fall outside after the shift.
Concept Introduction:Control charts are used to measure the effectiveness of the process determining the average value and control limits of the process. The Upper Control Limit (UCL) is the larger value and the Lower Control limit (LCL) is the smaller value of the sample
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A small electronic device is designed to emit a timing signal of 200.0 milliseconds (ms) duration. This device is specified as 201.0 + 10.0. In the production of this device, subgroups of six units are taken at periodic intervals and tested. Xbar and R are calculated for each subgroup and used to plot control charts. The results of inspection of 25 subgroups, ΣX = 5,000.00 and ΣR = 277.00.
Determine the control limits for Xbarand R charts, and estimate the value of σ.
Which of the following statements about Pareto diagrams is correct?a. The Pareto diagram shows the possible root causes of a problem along with the numberof defect occurrences.b. The Pareto diagram shows the process capability index over time.c. The Pareto diagram shows the mean of a random sample at various points in time.d. The Pareto diagram shows a visual representation of binary outcome variables.
At Webster Chemical Company, lumps in the caulking compound could cause difficulties in dispensing a smooth bead from the tube. Even when the process is in control, an average of four lumps per tube of caulk will remain. Testing for the presence of lumps destroys the product, so an analyst takes random samples. The following results are obtained:
Tube No.
Lumps
Tube No.
Lumps
Tube No.
Lumps
1
6
5
6
9
5
2
5
6
4
10
0
3
0
7
1
11
9
4
4
8
6
12
2
Determine the c-chart two-sigma upper and lower control limits for this process. Is the process in statistical control?
Chapter 12 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 12.1 - Prob. 2PCh. 12.1 - Prob. 3PCh. 12.1 - Prob. 4PCh. 12.1 - Prob. 5PCh. 12.1 - Prob. 6PCh. 12.2 - Prob. 7PCh. 12.2 - Prob. 8PCh. 12.2 - Prob. 9PCh. 12.2 - Prob. 10PCh. 12.2 - Prob. 11P
Ch. 12.2 - Prob. 12PCh. 12.2 - Prob. 13PCh. 12.3 - Prob. 14PCh. 12.3 - Prob. 15PCh. 12.3 - Prob. 16PCh. 12.3 - Prob. 17PCh. 12.4 - Prob. 18PCh. 12.4 - Prob. 19PCh. 12.4 - Prob. 20PCh. 12.4 - Prob. 21PCh. 12.5 - Prob. 22PCh. 12.6 - Prob. 23PCh. 12.6 - Prob. 24PCh. 12.6 - Prob. 25PCh. 12.6 - Prob. 26PCh. 12.6 - Prob. 27PCh. 12.6 - Prob. 28PCh. 12.9 - Prob. 29PCh. 12.9 - Prob. 30PCh. 12.9 - Prob. 31PCh. 12.9 - Prob. 32PCh. 12.9 - Prob. 33PCh. 12.10 - Prob. 34PCh. 12.10 - Prob. 35PCh. 12.10 - Prob. 37PCh. 12.10 - Prob. 38PCh. 12.10 - Prob. 39PCh. 12.10 - Prob. 40PCh. 12.11 - Prob. 41PCh. 12.11 - Prob. 42PCh. 12.11 - Prob. 43PCh. 12.11 - Prob. 44PCh. 12.12 - Prob. 46PCh. 12.12 - Prob. 47PCh. 12.12 - Prob. 48PCh. 12 - Prob. 49APCh. 12 - Prob. 50APCh. 12 - Prob. 51APCh. 12 - Prob. 52APCh. 12 - Prob. 53APCh. 12 - Prob. 54APCh. 12 - Prob. 55APCh. 12 - Prob. 57APCh. 12 - Prob. 58APCh. 12 - Prob. 59APCh. 12 - Prob. 60APCh. 12 - Prob. 61APCh. 12 - Prob. 62APCh. 12 - Prob. 63APCh. 12 - Prob. 64APCh. 12 - Prob. 65APCh. 12 - Prob. 66APCh. 12 - Prob. 67APCh. 12 - Prob. 68APCh. 12 - Prob. 69APCh. 12 - Prob. 70AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The specification for a plastic liner for concrete highway projects calls for a thickness of 6.0 mm ± 0.1 mm. The standard deviation of the process is estimated to be 0.02 mm. What are the upper and lower specification limits for this product? The process is known to operate at a mean thickness of 6.03 mm. What is the Cp and Cpk for this process? About what percent of all units of this liner will meet specifications?arrow_forwardWhich of the following statements about Pareto diagrams is correct?a. The Pareto diagram shows the possible root causes of a problem but does not show thefrequency of defect occurrences.b. The Pareto diagram shows the defects in order from most commonly occurring to leastcommonly occurring.c. The Pareto diagram shows the mean of a random sample at various points in time.d. The bars in the Pareto diagram have, on average, roughly the same height.arrow_forwardWith Six Sigma the goal is to reduce process variation to 10% of the design tolerance. True Falsearrow_forward
- Design specifications require that a key dimensions on a product measures 346=12 units . A process is being considered for producing this product has a standard deviation of eight units. The process average has been shifted to 350 so that the process capability is 0.3333. Approximately, what percentage of items produced will be defective?arrow_forwardThe output of a certain integrated-circuit productionline is checked daily by inspecting a sample of 100 units.Over a long period of time, the process has maintaineda yield of 80 percent, that is, a proportion defective of 20 percent, and the variation of the proportion defec-tive from day to day is measured by a standard devi-ation of 0.04. If on a certain day the sample contains 38 defectives, find the mean of the posterior distribu-tion of as an estimate of that day’s proportion defec-tive. Assume that the prior distribution of Θ is a beta distribution.arrow_forwardA pharmaceutical company producing vitamin capsules desires a proportion of calcium content between 40 and 55 ppm. A random sample of 20 capsules chosen from the output yields a sample mean calcium content of 44 ppm with a standard deviation of 3 ppm. Find the natural tolerance limits of the process. If the process is in control at the present values of its parameters, what proportion of the output will be nonconforming, assuming a normal distribution of the characteristic? Answer letters a, b, and c. a. Find the Cp index. Comment on the ability of the process to meet specifications. b. What proportion of the specification range is used up by the process? c. If it is easier to change the process mean than to change its variability, to what value should the process mean be set to minimize the proportion of nonconforming product?arrow_forward
- Which is an INCORRECT way to analyze the process capability of a process (on a particular quality characteristic) that is not normally distributed? a. Use Cp(q) b. None of those listed c. Transform the data to normal first and use the transformed data on indices such as Cp which work well on normally distributed data. d. Use Cpc e. Use Cpmkarrow_forwardThe Canine Gourmet Company produces delicious dog treats for canines with discriminating tastes. Management wants the box-filling line to be set so that the process average weight per packet is 49 grams. To make sure that the process is in control, an inspector at the end of the filling line periodically selects a random box of 7 packets and weighs each packet. When the process is in control, the range in the weight of each sample has averaged 7 grams. The UCLR equals .--------- grams and the LCLR equals --------- grams. (Enter your response rounded to two decimal places.) More Information Factors for calculating three-sigma limits for the x-chart and R-chart Size of Sample (n) Factor for UCL and LCL for x-chart (A2) Factor for LCL for R-Chart (D3) Factor for UCL for R-Chart (D4) 2 1.880 0 3.267 3 1.023 0 2.575 4 0.729 0 2.282 5 0.577 0 2.115 6 0.483 0 2.004 7 0.419 0.076 1.924…arrow_forwardAn acceptance sampling plan has lots of 500pieces and a sample size of 60. The number of defects in thesample may not exceed 2. This plan, based on an OC curve,has a probability of .57 of accepting lots when the incominglots have a defective rate of 4%, which is the historical averagefor this process. What do you tell your customer the averageoutgoing quality is?arrow_forward
- State True or False for the below two statements. 1. The purpose of process control charts is to detect the presence of natural variations. 2. Unlike process capability ratio (Cp), process capability index (Cpk) can possibly be negative.arrow_forwardAt Quick Car Wash, the wash process is advertised to take less than 7 minutes. Consequently, management has set a target average of 390 seconds for the wash process. Suppose the average range for a sample of 9 cars is 8 seconds. Use the accompanying table to establish control limits for sample means and ranges for the car wash process. LOADING... Click the icon to view the table of factors for calculating three-sigma limits for the x overbarx-chart and R-chart. Factors for calculating three-sigma limits for the x overbarx-chart and R-chart Size of Sample (n) Factor for UCL and LCL for x overbarx-chart (Upper A 2A2) Factor for LCL for R-Chart (Upper D 3D3) Factor for UCL for R-Chart (Upper D 4D4) 2 1.8801.880 00 3.2673.267 3 1.0231.023 00 2.5752.575 4 0.7290.729 00 2.2822.282 5 0.5770.577 00 2.1152.115 6 0.4830.483 00 2.0042.004 7 0.4190.419 0.0760.076 1.9241.924 8 0.3730.373…arrow_forwardAt Quick Car Wash, the wash process is advertised to take less than 7 minutes. Consequently, management has set a target average of 390 seconds for the wash process. Suppose the average range for a sample of 9 cars is 8 seconds. Use the accompanying table to establish control limits for sample means and ranges for the car wash process. LOADING... Click the icon to view the table of factors for calculating three-sigma limits for the x overbarx-chart and R-chart. Factors for calculating three-sigma limits for the x overbarx-chart and R-chart Size of Sample (n) Factor for UCL and LCL for x overbarx-chart (Upper A 2A2) Factor for LCL for R-Chart (Upper D 3D3) Factor for UCL for R-Chart (Upper D 4D4) 2 1.8801.880 00 3.2673.267 3 1.0231.023 00 2.5752.575 4 0.7290.729 00 2.2822.282 5 0.5770.577 00 2.1152.115 6 0.4830.483 00 2.0042.004 7 0.4190.419 0.0760.076 1.9241.924 8 0.3730.373…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.