Chapter 12.1, Problem 3P
Summary Introduction

Interpretation: Z score and Rejection probability needs to be calculated based on the given data.

Concept Introduction: Z score is an important statistical metric on basis of which probabilities can be calculated within normal distribution.

Blurred answer
Students have asked these similar questions
A manufacturer of programmable calculators is attempting to determine a reasonable free-service period for a model it will introduce shortly. The manager of product testing has indicated that the calculators have an expected life of 30 months. Assume product life can be described by an exponential distribution.  T / MTBF e-T /MTBF T / MTBF e-T /MTBF T / MTBF e-T /MTBF 0.10 0.9048 2.60 0.0743 5.10 0.0061 0.20 0.8187 2.70 0.0672 5.20 0.0055 0.30 0.7408 2.80 0.0608 5.30 0.0050 0.40 0.6703 2.90 0.0550 5.40 0.0045 0.50 0.6065 3.00 0.0498 5.50 0.0041 0.60 0.5488 3.10 0.0450 5.60 0.0037 0.70 0.4966 3.20 0.0408 5.70 0.0033 0.80 0.4493 3.30 0.0369 5.80 0.0030 0.90 0.4066 3.40 0.0334 5.90 0.0027 1.00 0.3679 3.50 0.0302 6.00 0.0025 1.10 0.3329 3.60 0.0273 6.10 0.0022 1.20 0.3012 3.70 0.0247 6.20 0.0020 1.30 0.2725 3.80 0.0224 6.30 0.0018 1.40 0.2466 3.90 0.0202 6.40 0.0017 1.50 0.2231 4.00 0.0183 6.50 0.0015 1.60 0.2019 4.10 0.0166 6.60 0.0014 1.70 0.1827 4.20…
A company is trying to determine the proper capacity level for its new electric car. A unit of capacity provides the potential to produce one car per year. It costs $15,000 to build a unit of capacity and the cost is charged equally over the next five years. It also costs $500 per year to maintain a unit of capacity (whether or not it is used). Each car sells for $20,000 and incurs a variable production cost of $15,000. The annual demand for the electric car during each of the next five years is believed to be normally distributed with mean 65,000 and standard deviation 12,000. The demands during different years are assumed to be independent. Profits are discounted at a 7.5% annual interest rate. The company is working with five-year planning horizon. Capacity levels of 30,000, 40,000, 50,000, 60,000, and 70,000 are under consideration. You can assume that the company never produces more than demand, so there is never any inventory to carry over from year to year. a. Assuming that the…
A company uses 85 circuit boards a day in a manufacturing process. The person who ordersthe boards follows this rule: Order when the amount on hand drops to 625 boards. Orders are delivered approximately six days after being placed. The delivery time is normal with a mean ofsix days and a standard deviation of 1.10 days. What is the probability that the supply of circuitboards will be exhausted before the order is received if boards are reordered when the amount onhand drops to 625 boards?
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,