Production and Operations Analysis, Seventh Edition
Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
bartleby

Concept explainers

Question
Book Icon
Chapter 12, Problem 67AP

a

Summary Introduction

Interpretation:

Acceptability of heavy duty nails lot

Concept Introduction:

Normal distribution is the probability function with continuous series. It is bell shaped distribution function where mean, median and mode are same.

a

Expert Solution
Check Mark

Answer to Problem 67AP

  α is 0.0803 and β is 0.0028.

Explanation of Solution

Given information:

n = 100

c= 2

AQL = 1%

LTPD = 10%

  α=0.0803 as = 10000

and β=0.0028 are the producers and consumers risk factor respectively. α , represents the probability that a sampling plan might reject the good lot whereas β , represents the probability that a sampling plan might accept the bad lot.

Lot size, N=10,000

Accepted Quality Level (AQL) is 1%

Lot Tolerance Percent Defective (LTPD) is 10%

  pο=0.01p1=0.10

  α=P{X>c/p=1,n=100}

  =P{X>2/θ=1}=0.0803

  β=P{X£/p=0.1,n=100}

  =P{X£2/θ=10}=0.0028

Hence, α is 0.0803 and β is 0.0028.

b

Summary Introduction

Interpretation:

Sequential sampling plan

Concept Introduction:

Normal distribution is the probability function with continuous series. It is bell shaped distribution function where mean, median and mode are same.

b

Expert Solution
Check Mark

Answer to Problem 67AP

Sequential sampling plan with two limit lines are xa=2.42+0.0394n and xt=1.051+0.0397n

Explanation of Solution

Given information:

n = 100

c= 2

AQL = 1%

LTPD = 10%

  α=0.0803 as = 10000

Computation of two lines

Calculate the values of k, h1 and h2 by using the following formula.

  k=log[p2(1 p 1)p1(1 p 2)].....(1)

  h1=1k[log(1αβ)].....(2)

  h2=1k[log(1βα)]......(3)

  s=1k[log(10.0110.10)]....(4)

Information known as per the problem

  p1=0.01p2=0.10α=0.0803β=0.0028

Now, substitute these values in equation (1) to calculate k as shown below

  k=log[p2(1 p 1)p1(1 p 2)]

  =log[0.10(10.01)0.01(10.10)]

  =log0.0990.009=log11=1.041

Now, substitute these values in equation (2) to calculate h1 as shown below:

  h1=1k[log(1αβ)]

  =11.041[log(10.08030.0028)]

  =11.041[log(0.91970.0028)]

  =0.96(log328.46)=0.96×2.52=2.42

Now, substitute these values in equation (3) to calculate h2 as shown below:

  h2=1k[log(1βα)]

= 10.041[log(10.00280.0803)]

  =11.041[log( 0.9972 0.0803)]=0.96(log12.42)=0.96×1.095=1.051

Similarly, substitute these values in equation (4) to calculate s as shown below:

  s=1k[log(10.0110.10)]

  =11.041[log(0.990.90)]

  =0.96[log(1.1)]

  =0.96×0.0413=0.0397

Calculate the two limit lines by substituting the values of 2.42, 1.051 and 0.0397 in the h1 , h2 and s respectively in the below formulae.

  xa=h1+sn

  xt=h2+sn

  xa=2.42+0.0394n

  xt=1.051+0.0397n

Hence, the two limit lines are xa=2.42+0.0394n and xt=1.051+0.0397n .

c

Summary Introduction

Interpretation:

Maximum value of the expected sample size

Concept Introduction:

Normal distribution is the probability function with continuous series. It is bell shaped distribution function where mean, median and mode are same.

c

Expert Solution
Check Mark

Answer to Problem 67AP

The maximum expected number of items which must be sampled is probably less than 75.

Explanation of Solution

Given information:

n = 100

c= 2

AQL = 1%

LTPD = 10%

  α=0.0803 as = 10000

At p=0 ASN=60.86

At p=0.1 ASN=71.97

At p=0.0397 ASN=66.6

Based on this, the maximum expected number of items which must be sampled is probably less than 75.

d

Summary Introduction

Interpretation:

Graphical representation of acceptance and rejection region and check whether sequential sampling plan would recommend acceptance or rejection on or before testing 100th nail.

Concept Introduction:

Normal distribution is the probability function with continuous series. It is bell shaped distribution function where mean, median and mode are same.

d

Expert Solution
Check Mark

Explanation of Solution

  Production and Operations Analysis, Seventh Edition, Chapter 12, Problem 67AP

Hence, acceptance would be recommended on 61st nail.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Consider the following double sampling plan. First select a sample of 5 from a lotof 100. If there are four or more defectives in the sample, reject the lot. If there isone or fewer defective, accept the lot. If there are two or three defectives, samplean additional five items and reject the lot if the combined number of defectives inboth samples is five or more. If the lot has 10 defectives, what is the probabilitythat a lot passes the inspection? For the double sampling plan described in Problem 39, determine the following:b. The probability that the lot is rejected based on the second sample.
A company employs the following sampling plan: It draws a sample of 10 percentof the lot being inspected. If 1 percent or less of the sample is defective, the lot isaccepted. Otherwise the lot is rejected.b. If a lot contains 1,000 items of which 20 are defective, what is the probabilitythat the lot is accepted?
A single sampling inspection scheme for large lot of mass-produced flanges states:From each lot take and inspect a random sample of 50. If 3 or more defectives, inspect the whole lot and remove all defectives, if less than 3 are found accept the lot without further inspection.a. Obtain the equation for Pa the probability that a lot containing a fraction p of defectives will be accepted, in terms of p.b. Evaluate Pa for p=0.01, 0.02, 0.03, 0.05, 0.07, 0.10, 0.15, 0.20, 0.30. Plotthe operating characteristics and average outgoing quality curve.c. Estimate: (a) the producer’s Risk at p of 2% (b) the consumer’s Risk for pof 5%.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.